Building Time Frames Are Quicker Than You May Think
Once you have decided on a lot and house plan, here is what you can expect:
Step 1 (Day 1)
We sit down have the first of 5 meeting together. At this time, concentrate on getting the home started and just think about the following questions:
- The position of the home on the lots
- The elevation of the home
- The type of windows to be used
Step 2 (Day 30)
The starting of the foundation for the home. We will now meet for a second time to finalize the following:
- The position of the home on the lots
- The elevation of the home
- The type of windows to be used
Step 3 (Day 50)
We should be framing at this point, we will meet a third time to finalize the following:
- All electrical placement
- All heating and cooling items
- All plumbing specifications
- Cabinets to be used
- And finally all insulation and drywall questions and concerns
Step 4 (Day 105)
At our fourth meeting we should be installing drywall and at this time we need to finalize the rest of the interior colors and material types. We will need to finalize:
- Trim package
- Paint colors
- Ceramic tiles
- Counter tops
- Electrical fixture package
- Plumbing fixture package
- Flooring selections
Step 5 (Day 150)
We should be completed with your home and be presenting the home to you for your inspection, your home orientation and how to operate all its special features. We will have a closing day set, or if not this date should get finalized soon.
This is the Women-Centric approach to building a new home. We try to keep the process organized for you. We have you concentrate on the questions we need answers to now and give you time to make the rest of your choices later. To ask you to make all of your decisions at one time makes the process stressful and not fun. We constantly meet with you and help guide you through the home building process.
The process is all about you.
American Heartland does this for you so that the process doesn't overwhelm you.
|